This project involves the construction of a new extenion building
| Client | Vion Foods UK Ltd |
| Design Team | CDM Coordinator / Cost Consultant – Cyril Sweett Group Designers – Teague & Sally Ltd M&E Engineers – Aecom |
| Contract Value | £0.5M |
| Contract Duration | 29th August 2011 to 10thFebruary 2012 |
| Project Description | Construction of new extension stunner building – which includes · The relocation of existing services between bund and external stairs to gas tanks · Bulk excavation and pouring concrete retaining walls · New bases/plinths for C02 tanks and new C02 tank · New road to black gut area · Lay new services/drainage to all of new buildings · Construct new stunner pit 10m deep · Remove roof cladding and existing stunner · Clad roof of existing and new extension building · Alteration of internal low level walls in existing lairage building |