GEDA - Civil Engineering - Waste water Treatment Works upgrade

Skip Navigation

Civil Engineering - Waste water Treatment Works upgrade

View all Civil Engineering Schemes

Waste water Treatment Works upgrade, Coagh

Design and build works involving the upgrade of the existing wastewater treatment works. The existing works require upgrading to achieve the required NIEA discharge standards.

Client:NI Water
Consultant:RPS/MWTL
  
  
  
Contract Duration:40 weeks
Brief Description:

Works will include the construction of new inlet works (including CSO and flow control devices), inlet screening, grit and grease removal, primary settlement tanks. RBC Treatment Process, Final Settlement Tanks and Storm and Sludge Holding Tanks have also to be constructed.

Works also include a final effluent pumping station, ancillary pipework, MCC Structure, Standby Generator and associated site works.

Following commissioning on the new works redundant structures are decommissioned and demolished with concrete crushed and re-used on-site as fill material.                

NI Water and GEDA have developed a robust Environmental Management Plan to meet NIEA requirements for the contract which means that all possible measures will be undertaken to ensure that the construction work does not adversely impact on the adjacent watercourses.