Construction of new inlet works, four retention tanks and pumping stations with associated works. This also included the laying of sewers and watermains in a residential area
| Client: | DRD Water Service (Michael McGivern) |
| Consultants: | RPS Consulting |
| 74 Boucher Rd | |
| Belfast | |
| BT12 6HR | |
| +44 (0)28 9066 7914 (Malcolm Brian) | |
| Contract Value: | £3.1M |
| Contract Duration: | Apr 02 – Feb 04 |
| Brief Description: | The project was carried out for D.R.D. Water Service with Kirk McClure Morton acting for the client and Geda Construction responsible for the complete construction works. |
| The works included the construction of a new inlet works and storage at Seahill WwTW and the construction of four reinforced concrete retention tanks and pumping stations on separate sites together with the various buildings, access roads, fencing and site works. | |
| The works included the laying of some 8km of sewer pipelines and 4km of water mains. | |
| As the construction work was in a residential area, customer care had high priority with detailed planning, liaison, phasing and co-ordination not just of our own works but also of NIE, Phoenix Gas and BT who were also carrying out utility work in the same area at the same time. | |